Fastener Manufacturing Process

Production process: cut → head → thread roll → heat treat → finish → inspect and pack, with process controls below; plus the five-gate criteria and measured data for replacing machining with cold heading — the most direct cost-down route for volume rotationally-symmetric parts.

Fastener Manufacturing Process

Process controls

  • Heading: die life and first-article checks
  • Heat treat: hardness and metallography sampling
  • Finishing: coating thickness and salt spray per batch
  • Shipment: AQL sampling with reports

Cold heading vs CNC: five dimensions

FactorCold heading (forming)CNC (cutting)
Material utilisationHigh — only setup scrapLow — chips on every part
Grain flowContinuous along the contourCut by tools, forming weak planes
Strength (same material)Clearly better (work hardening + continuous flow)Yield/tensile reduced
Cycle timeSeconds per part — orders of magnitude fasterSlow
Upfront costHigher die cost, 6–12 h changeoverMinimal die cost, 2–4 h setup
Volume costLower with volumeSuits first articles and small batches
Geometric freedomLimited by forming envelopeHighest freedom

Grain flow: cold-headed parts are stronger (measured)

SizeSteelMachined tensile kgf/mm²Cold-headed tensile kgf/mm²Gain
M8Steel 406268≈ +9.7%
M10Steel 355660≈ +7.1%
M12Steel 40X6065≈ +8.3%
M18Steel 355257≈ +9.6%
Source: Tensile comparison of machined vs cold-headed parts, same material and size. Source: internal process test records.

Five gates: decide by calculation, not habit

GateQuestionCriterion
Gate 1 · DeformationCan the material take it?Deformation degree q below material limit (low-carbon steel 60–70%; high-carbon only 20–30%)
Gate 2 · BlowsHow many blows?Free-upset ratio S=L/D: ≤2.5 one blow, ≤4.5 two, ≤6.5 three
Gate 3 · Shank bucklingWill the shank bend?Solid-die shank length ≤8d; longer → open die or secondary machining
Gate 4 · Machine capabilityIs the machine enough?Check wire diameter, cut length and forming force — not just “head size”
Gate 5 · Wire qualityDoes the wire qualify?Incoming checks: Brinell hardness, tensile, elongation, reduction of area

Extrusion deformation limits

ModeArea reduction per passExtrusion angleTypical use
Open extrusion (billet pushed into a small-hole die)≤30%≤30°Bolts, screws, stepped shafts
Closed (confined) extrusionUp to 75%Larger head-to-shank ratiosNuts, sleeves, semi-tubular rivets

Hybrid route: form by heading, finish by machining

  • Forming by heading: keep grain flow and work-hardening gains — over 90% of material becomes part, not chips
  • Precision by machining: finish-turn/grind only critical fits and GD&T features, shrinking allowances
  • Typical chain (SUS630 / 17-4PH): solution-annealed wire → multi-station near-net heading → thread rolling → ageing → light finishing; ageing shrinks parts 0.04–0.06%, so precision machining comes after ageing
  • Economics: machining time drops to a few features while utilisation and cycle time stay cold-heading-grade — the bigger the batch, the bigger the gain

Typical cases

  • 6061 battery-pack lifting sleeve: full CNC from bar cuts aluminium grain flow, leaving weak points under cyclic stress; cold heading keeps flow continuous around flange and body with higher stress-fracture resistance — safety redundancy for a point carrying the whole pack
  • VA/VE process change: forged→cold-headed project saved ¥0.75/unit internally, ¥375,000 over 500k pieces

Three contact tiers

Phones and mailbox are identical site-wide and match the structured data.

Three contact tiers
NeedContactReach
Technical · Engineering review Mr. Zhang (Engineering & Sales Director) +86 135-1036-9429 [email protected]
Sales · Quotes / MOQ / lead time Ms. Fan (Sales Manager) +86 135-6073-0094 [email protected]
Complaints & suggestions Complaints & suggestions (reply within 24 h) [email protected]

FAQ

Cold heading or CNC?
Flanged rotational parts at volume suit heading (grain flow, cycle time, utilisation); complex geometry, small batches or many precision features go CNC or the hybrid route. Always pass the five gates first.
How to start a cost-down review?
Send the part drawing and annual volume; we return a process route and savings estimate within one working day. Small-batch samples can run in as fast as 1 day.

Need a spec check or 1-day sample?

Send us your drawing, spec or part code. We reply the same day on stock, MOQ, tiered pricing and lead time (1-day sampling for stock; volume 7–15 days).

Call directly: +86 135-1036-9429(Mr. Zhang (Engineering & Sales Director)) · +86 135-6073-0094(Ms. Fan (Sales Manager))